Act 255 changed Louisiana’s public prompt-payment rules, and on public projects it changes the balance of leverage in a real way. It took effect May 15, 2026.
The core change: A public owner can no longer hold back liquidated damages the contractor disputes. If the owner believes it is owed delay damages, it has to pay the contractor first and pursue the claim in a separate lawsuit. The one exception is narrow — flood protection and integrated coastal projects — and it opens only after the standard 45-day payment window closes.
This is less a reversal than a codification. Louisiana courts had previously ruled that a public entity could not sit on a contractor’s retainage over an unproven delay claim, and that a contract clause purporting to allow it did not override the duty to pay. Act 255 now writes that into the statute and names contested liquidated damages directly, so the outcome no longer turns on how a court may read the older law.
Three features give teeth to Louisiana Act 255:
Bottom line: Contractors holding receivables against an open delay assessment should revisit them now, and public owners should treat liquidated damages as a claim to prove in court, not a reason to withhold.